Construction Details
When complete, 219 Langdon will feature several prominent upgrades, making it a very attractive housing choice for Lambda undergraduate members. The construction details are as follows:

Chapter House Facility
- A new, traditional façade on the front of the street.
- A complete re-plumbing of the water and sewage systems.
- A completely new electrical system.
- A new HVAC system that includes heating and cooling.
- High performing wireless internet connectivity.
- Installation of a commercial kitchen for a full chapter dining program.
- Structural renovation on the rooftop deck.
- Paving the parking lot to meet city code regulations.
Parking Lot
- Fully paved lot.
- Updated lighting.
- Required green space.
- Traffic flow running clockwise due to the existing hydrant and utility pole at Lake Lawn.
- Basketball court in southeast corner.
- Trash enclosure is sized to fit the current dumpster.
Overall Constrution Timeline
- Summer of 2018 - Parking Lot
- January 2019 - House Design Start
- January 2020 - Bidding
- May 2020 - Construction Start
- December 2020 – March 2021 - Completion, depending on phasing
Construction Budget
Building Improvements and Repairs |
$1,722,729 |
Parking lot Improvements |
$140,000 |
Roof Improvements |
$596,250 |
Current Mortgage to refinance |
$380,000 |
Fixed costs to recover while vacant |
$50,000 |
Capital Campaign Costs |
$200,000 |
Total Project Cost |
$3,088,979 |
|
|
Capital Campaign Donations |
$1,000,000 |
Amount to finance |
$2,088,979 |